| # | Date Created | Employee | Work Type | Task | Duration (Hours) | Action |
|---|---|---|---|---|---|---|
| 1 | 2025-01-15 03:54 | Pravin Lonkar | Testing | Channel1 ABS testing support. |
4.00 | |
| 2 | 2025-01-08 16:37 | Pravin Lonkar | VAT Database | Sku Number NR191020 added for PCM Bosch & ABS Conti CH-1 in INEL database for ABS Static station testing. |
1.50 | |
| 3 | 2025-01-02 07:31 | Pravin Lonkar | Client (External) Meetings | Discussion with TVS Team regarding DTC getting logged in Bosch PCM. Explained in detail on how decoding is done for DTC. |
1.00 | |
| 4 | 2024-11-28 18:26 | Pravin Lonkar | Team Coordination / Technical Support | Fogbugs raised with US Team for DW2 firmware issue in communication with ABS Conti |
2.00 | |
| 5 | 2024-11-28 18:19 | Pravin Lonkar | Testing | ABS conti testing for DW2 communication issue identification and fixing. |
8.00 | |
| 6 | 2024-11-28 18:15 | Pravin Lonkar | Bug Fixing | Trials taken with different Hardware and Module config item combination to resolve the ABS Conti communication issue. |
5.00 | |
| 7 | 2024-11-28 18:08 | Pravin Lonkar | Testing | Testing for DW2 VCI communication issue with ABS Conti ECU. |
6.00 | |
| 8 | 2024-11-28 18:04 | Pravin Lonkar | Testing | ABS Channel 1 Static Sequence testing for DW2 VCI Communication Issue. |
6.00 | |
| 9 | 2024-10-27 20:22 | Pravin Lonkar | VAT Database | Conti ABS CH-1 sequence development. |
5.00 | |
| 10 | 2024-10-27 20:15 | Pravin Lonkar | VAT Database | ABS conti CH-1 station sequence development. |
8.00 | |
| 11 | 2024-10-27 20:04 | Pravin Lonkar | VAT Database | Conti ABS CH-1 Static sequence development. |
4.00 | |
| 12 | 2024-10-27 19:20 | Pravin Lonkar | Client (External) Meetings | Discussion with TVS team on ABS-Ch-1 Static station sequence development. |
4.00 | |
| 13 | 2024-10-27 19:06 | Pravin Lonkar | VAT Database | ABS Conti Ch-1 Static sequence development. |
8.00 |